# Major Developments

  • The planned production release for the FirebasetoAWS migration (Boukili) scheduled for Monday was cancelled; no new release date will be set until blockers are clarified and reliable estimates obtained. (Source: 20 Work/Projects/2026/Boukili/2026-09-10 - Boukili.md)
  • A “freeze” of code will occur once the currently identified issues are fixed and validated; phase2 work will be kept on a separate branch and not merged into phase1 during validation. (Source: 20 Work/Meetings/TFO/Produits Numériques (Transversal)/2026-09-11 - Produit Numérique.md)
  • The OTT delivery is at risk of missing the liveevent deadline (Sept14) due to regressions; a weekend release may be required to meet the Sept17 live broadcast. (Source: 20 Work/Meetings/Team Meetings/2026/2026-09-10 - Reunion equipe.md)

# Risks / Blockers

  • Potential loss or nonsynchronisation of user data for multidevice users during the FirebasetoAWS migration; risk heightened if devices remain on different backends. (Source: Boukili.md)
  • Ongoing Salesforce regression investigation with no resolution at time of meeting; impacts data migration reliability. (Source: Boukili.md)
  • Uncertainty about the reliability of the data migration itself; current suggested solutions (accepting data loss or reduced reliability) are not acceptable. (Source: Boukili.md)
  • Insufficient testing time to guarantee a solid version before submission; migration works on test/staging but fails on UAT. (Source: Produit Numérique.md)
  • “Last activity” field reliability issues, especially under network failure conditions. (Source: Produit Numérique.md)
  • Undefined strategy for forced migration of multidevice users; critical for submission. (Source: Produit Numérique.md)
  • QA capacity bottleneck: only one QA resource covering four sites; risk of delayed testing. (Source: Reunion equipe.md)
  • JW Player billing ambiguity: unclear whether fees apply to active address or actual stream usage. (Source: Direct ONFR - Réponse sur le feed de JWP.md)

# Decisions Made

  • Cancelled Monday production release for Boukili migration; defer new date pending clarification. (Source: Boukili.md)
  • Code freeze to be applied after fixing and validating identified issues; phase2 work isolated on separate branch. (Source: Produit Numérique.md)
  • Use the second Corus feed for a test send to JW Player; keep existing feed unchanged; retain both ingest points and request JW Player to delete those that cannot be removed directly. (Source: Direct ONFR - Réponse sur le feed de JWP.md)
  • Documentation departmental will be presented under “platform” section; data governance treated as continuous practice; project renamed “projet Données FMC”. (Source: Reunion equipe.md)
  • For Idéllo ZIP files, each course/ZIP must have its own Jira ticket; processing will not start before 12Oct. (Source: Reunion equipe.md)

# Decisions Needed

  • Confirmation of the migrationforced strategy for multidevice users and associated user communication plan. (Source: Produit Numérique.md)
  • Final delivery date and freeze trigger confirmation for the upcoming release (window18Sept  23Sept). (Source: Produit Numérique.md)
  • Clarification of JW Player billing conditions (address active vs. stream usage). (Source: Direct ONFR - Réponse sur le feed de JWP.md)
  • Approval of additional QA resources or temporary reinforcement to address capacity bottleneck. (Source: Reunion equipe.md)

# Project Changes

  • Production schedule for Boukili migration postponed; new schedule pending resolution of datamigration blockers. (Source: Boukili.md)
  • OTT delivery timeline now uncertain; may require weekend release to meet live event on 17Sept. (Source: Reunion equipe.md)
  • Phase2 development work will be isolated on a separate branch, not merged into phase1 during validation. (Source: Produit Numérique.md)

# Vendor Issues

  • JW Player billing details remain contradictory; need clarification from vendor. (Source: Direct ONFR - Réponse sur le feed de JWP.md)
  • Coordination with Corus (contact Chris Sandinot) required to modify second stream address for test. (Source: Direct ONFR - Réponse sur le feed de JWP.md)

# Team / Coaching / Recognition

  • No explicit coaching or recognition items identified in the notes.

# NextWeek Commitments

  • Technical point with Abiba to clarify datamigration issues (deadline: tomorrow morning). (Source: Boukili.md)
  • Prepare and circulate email detailing critical blockers for team validation. (Source: Boukili.md)
  • Evaluate feasibility, cost, and timeline of IBO intervention on migration with The Mind (starting after tomorrows point). (Source: Boukili.md)
  • Inform Mohamed of the release postponement after clarification with Abiba. (Source: Boukili.md)
  • Obtain duration estimates for resolving remaining problems (responsible: The Mind). (Source: Boukili.md)
  • Investigate UAT migration issue and deliver a stable version after a new test cycle (development team). (Source: Produit Numérique.md)
  • Implement retry mechanism for “last activity” field and set up visibility indicator for tests (development team). (Source: Produit Numérique.md)
  • Exchange with Habiba to define robust solution for validating last activity (responsible: relevant teams). (Source: Produit Numérique.md)
  • Study with current agency the possibility of forcing all users to update via Contentful message (Amadou & team). (Source: Produit Numérique.md)
  • Verify Salesforce test progress with Nicolas and Mark; communicate update (responsible: relevant team). (Source: Produit Numérique.md)
  • Confirm realistic delivery dates by email (development team, due afternoon). (Source: Produit Numérique.md)
  • Prepare project presentation for meeting with Francis (due Tuesday15Sept). (Source: Reunion equipe.md)
  • Continue Umami tracker implementation (JeanClaude). (Source: Reunion equipe.md)
  • Analyze Mogador sync flows and set up failure alerts (Mohamed Slimane). (Source: Reunion equipe.md)
  • Create Jira tickets for each Idéllo ZIP file/course starting 12Oct (Jason & requestors). (Source: Reunion equipe.md)
  • Perform targeted regression tests on TFO live/carousel delivery before 1617Sept (Ajar). (Source: Reunion equipe.md)
  • Conduct exchange on servicetracking recommendations for MAMI (Rabiba & Amandou). (Source: Reunion equipe.md)
  • Test second Corus feed to JW Player and report results (responsible not specified). (Source: Direct ONFR - Réponse sur le feed de JWP.md)

# Sources

  • 20 Work/Projects/2026/Boukili/2026-09-10 - Boukili.md — production release cancellation, blockers, actions.
  • 20 Work/Meetings/TFO/Produits Numériques (Transversal)/2026-09-11 - Produit Numérique.md — code freeze, delivery window, risks.
  • 20 Work/Meetings/Team Meetings/2026/2026-09-10 - Reunion equipe.md — OTT delivery risk, Boukili migration complexity, QA capacity, project naming, Idéllo ZIP process.
  • 20 Work/Projects/2026/OTT/2026-09-10 - Direct ONFR - Réponse sur le feed de JWP.md — JW Player feed test, billing ambiguity.