## Risks / Attention
|
|
|
|
### QA capacity - upcoming projects
|
|
**Status:** 🔴 High
|
|
|
|
Four major projects are expected to reach QA close together.
|
|
|
|
Current QA capacity: 1 person.
|
|
|
|
**Risk:** QA becomes a bottleneck, delaying project delivery even if development finishes on schedule.
|
|
|
|
**Proposed mitigation:** Temporary freelance QA support during the overlapping QA period.
|
|
|
|
**Discuss with CTO:** 2026-07-27
|
|
|
|
**Next step:** Confirm approximate QA windows for the four projects.
|
|
|
|