🎯 Executive Summary
Overall health: Not assessed.
Traffic light: 🟡
This week's headline:
Multiple critical projects (Boukili migration, ONFR live‑feed, OTT launch, and WordPress hosting) face blockers and pending decisions that affect delivery schedules and vendor compliance.
Wins 🏆
- Boukili v3 finalized; testing schedule launched.
- “Set‑focus” trigger in Storyline completed (on standby).
- ONFR live‑feed testing to use Haywire feed; second Chorus URL deferred.
- Job‑supervision solution approved; phased rollout begins with ONFR.
- OTT search‑result ranking changes implemented; device testing underway.
- Decision to retain WordPress on current site and keep WP Engine as host.
- ZIP‑to‑Idéllo publishing workflow defined (ticket → ZIP → Hélène).
- CTO approved exploratory discussion with Lunii.
- Code freeze planned after fixing identified issues; phase‑2 isolated.
Risks ⚠️
- Storyline “set‑focus” compatibility with JAWS unknown → possible product delay.
- CRTC report lacks clarity on retroactivity, content, and publication location; deadline 5 Oct pending.
- Variable episode lengths may cause incorrect JWP recording stops → manual fixes needed.
- Subtitles not displaying for test videos (missing collection association).
- JWP ingest point & billing unclear for secondary feed; risk of unexpected fees.
- No staging server for supervision‑solution testing → production issues possible.
- Boukili production DB & Contentful API access unresolved, blocking full integration.
- Podcast automation still depends on Jira API connection.
- Geo‑blocking for TFO/Idéllo cannot be removed without release → legal compliance risk.
- Mogador synchronization complexity; source‑of‑truth undefined, possible project removal.
- US‑based vendor compliance (JWP, WP Engine, Algolia) under policy review.
- OTT delivery at risk of missing live‑event deadline; may require weekend release.
- QA capacity limited to one resource across four sites → testing delays.
- Firebase‑to‑AWS migration (Boukili) blocked by data‑migration reliability and Salesforce regressions; production release cancelled.
Team 👥
Team health
Overall morale: Not assessed.
Coaching / Recognition
- No explicit coaching or recognition items recorded.
Projects 📁
| Project | Status | Next Milestone | Blocker |
|---|---|---|---|
| Boukili v3 | Testing started | Begin version 3 testing (this week) | Access to production DB & Contentful API; migration data‑validation issues |
| Storyline “set‑focus” | Completed, on standby | Verify JAWS compatibility | Compatibility unknown |
| ONFR live‑feed | Haywire feed selected for tests | End‑to‑end broadcast test (10 h start) | JWP ingest‑point behavior & billing clarification |
| Job supervision solution | Approved, phased rollout | Deploy cron checks on ONFR | No staging server for testing |
| OTT search‑result ranking | Changes applied | Complete multi‑device testing (incl. Apple TV zoom) | OTT testing timeline tight; risk to live event |
| WordPress site | Hosting decision retained | Ongoing maintenance | None reported |
| ZIP‑to‑Idéllo workflow | Defined | Start processing tickets after 12 Oct | None reported |
| Lunii collaboration | Approved for exploratory talk | Present to CEO | Decision pending CEO review |
| Mogador sync | Discussion scheduled 16 Sept | Resolve synchronization approach | Complexity & lack of source‑of‑truth |
Vendors 🤝
- JWP: Billing model for secondary feed unclear; ingest‑point behavior under review.
- WP Engine: Hosting retained; no immediate issues.
- Algolia: Regression review pending (Trings invoice unblocked).
- US‑based vendors (JWP, WP Engine, Algolia) under compliance review per policy.
Decisions Made
- Keep Storyline “set‑focus” on standby until screen‑reader compatibility confirmed.
- Use Haywire feed for ONFR testing; defer second Chorus URL.
- Deploy supervision checks first on ONFR, then Idéllo, then TFO.
- Maintain JWP 24/7 feed unchanged; manage secondary test feed manually.
- Preserve Boukili on a dedicated VM; postpone API integration.
- Retain WordPress on current site with WP Engine hosting.
- Implement ZIP‑to‑Idéllo workflow with ticket‑based hand‑off to Hélène (start 12 Oct).
- Approve exploratory Lunii discussion with CEO.
- Code freeze after fixing identified issues; isolate phase‑2 work.
Decisions Needed
- Clarify CRTC report requirements (retroactivity, content, location) with Pierre‑Olivier.
- Confirm JWP ingest‑point behavior and any secondary‑feed fees.
- Decide if a second Chorus URL will ever be purchased.
- Determine final handling of ONFR live‑event streams (retain JWP vs. replace).
- Approve Jira‑form design for automated podcast‑chain requests (feasibility with Marc).
- Resolve geo‑blocking removal for TFO/Idéllo (legal compliance).
- Finalize Mogador synchronization approach or project removal.
- Choose which of the four technical subjects (retry, Firebase lockout, update‑message migration, Contentful version control) to include in next Boukili build.
- Confirm migration‑forced strategy for multi‑device users and communication plan.
- Approve additional QA resources or temporary reinforcement.
Top Priorities Next Week
- Send clarification email to CRTC and follow up with Pierre‑Olivier.
- Begin Boukili v3 testing and map production‑DB fields.
- Execute end‑to‑end ONFR broadcast test and add supervision cron entries.
- Verify JWP secondary‑feed billing and ingest‑point details.
- Create test collection in JWP and confirm subtitle display.
- Conduct OTT multi‑device testing (including Apple TV zoom) for sign‑off.
- Prepare ZIP‑to‑Idéllo tickets (ready for 12 Oct start).
CTO Development
Leadership: –
Technology: –
Business: –
Finance: –
Communication: –
One thing I did this week that made me more like a CTO: –
One thing I did this week that kept me acting like an individual contributor: –